Project

General

Profile

Calendar

Filters

« January | March »

Apply Clear

SundayMondayTuesdayWednesdayThursdayFridaySaturday
5

26

27

28

29

30

31

1

6

2

3

4

5

6

7

RK-A2 - Task #3790: Adjust wait time of fetchin... Task #3790: Adjust wait time of fetching DOM elements in FE Selenium tests.

Project: RK-A2
Status: Feedback
Start date: 02/07/2025
Due date:
Assignee: Shubham Boke
Priority: High
RK-A2 - Task #3789: Debug and Resolve the faile... Task #3789: Debug and Resolve the failed FE Selenium tests

Project: RK-A2
Status: New
Start date: 02/07/2025
Due date:
Assignee:
Priority: Normal
RK-A2 - Task #3788: Resolve FE selenium tests f... Task #3788: Resolve FE selenium tests failing due responsiveness check.

Project: RK-A2
Status: Review
Start date: 02/07/2025
Due date:
Assignee: Randheer Dagar
Priority: Normal
RK-A2 - Task #3786: Ensure all automated FE tes... Task #3786: Ensure all automated FE tests pass both in local and on QA

Project: RK-A2
Status: New
Start date: 02/07/2025
Due date:
Assignee:
Priority: High

8

7

9

10

11

RK-A2 - Task #3792: Unmock call to get_file GCF... Task #3792: Unmock call to get_file GCF (via rk2_gcf) if automated test is called with test_gcf flag as true

Project: RK-A2
Status: New
Start date: 02/11/2025
Due date:
Assignee:
Priority: Normal
RK-A2 - Feature #3791: Support for creating answer... Feature #3791: Support for creating answer choices for non-MCQ (VSA, LA) questions

Project: RK-A2
Status: Feedback
Start date: 02/11/2025
Due date:
Assignee: Shubham Boke
Priority: High

12

13

14

15

8

16

17

RK-A2 - Task #3795: Remove need to upload qna-<... Task #3795: Remove need to upload qna-<board>-<grade>-<subject>-<chapter num>.txt

Project: RK-A2
Status: Review
Start date: 02/17/2025
Due date:
Assignee: Shubham Boke
Priority: Urgent

18

19

RK-A2 - Task #3796: Support for subquestions Task #3796: Support for subquestions

Project: RK-A2
Status: New
Start date: 02/19/2025
Due date:
Assignee:
Priority: High

20

RK-A2 - Feature #3797: Support for detailed answer... Feature #3797: Support for detailed answers in 3772 colab

Project: RK-A2
Status: Review
Start date: 02/20/2025
Due date:
Assignee: Shubham Boke
Priority: High

21

RK-A2 - Feature #3798: End-end support for substep... Feature #3798: End-end support for substeps (such as step x.y)

Project: RK-A2
Status: Review
Start date: 02/21/2025
Due date:
Assignee: Dewakar Chaubey
Priority: High

22

9

23

24

25

26

27

RK-A2 - Task #3799: Remove the need for k12-sup... Task #3799: Remove the need for k12-support.txt except to check for supported-themes

Project: RK-A2
Status: Review
Start date: 02/27/2025
Due date:
Assignee: Dewakar Chaubey
Priority: High

28

RK-A2 - Bug #3801: Support for prefix-sub-ques... Bug #3801: Support for prefix-sub-question, prefix-question-multi-answer, prefix-sub-question-multi-answer

Project: RK-A2
Status: Review
Start date: 02/28/2025
Due date:
Assignee: Shubham Boke
Priority: High
RK-A2 - Task #3800: Add support in "3772 colab"... Task #3800: Add support in "3772 colab" to read and save back to DS

Project: RK-A2
Status: New
Start date: 02/28/2025
Due date:
Assignee:
Priority: High

1

RK-A2 - Task #3802: Support in 3772 colab for M... Task #3802: Support in 3772 colab for MCQs with multiple answers

Project: RK-A2
Status: Review
Start date: 03/01/2025
Due date:
Assignee: Shubham Boke
Priority: High

issue beginning this day issue ending this day issue beginning and ending this day